Title: Notice of Completion of Contract and Acceptance of Work for the Lower Silver Creek Flood Protection and Creek Restoration Project, Reaches 5C to 6A (Construction Phase - Milestone 1), Proven Management, Inc., Contractor, Project No. 40264008, Contract No. C0580 (San Jose) (District 6).
Attachments: 1. Attachment 1: Notice of Completion, 2. Attachment 2: Contract Acceptance, 3. Attachment 3: Completion Letter, 4. Attachment 4: PowerPoint, 5. Attachment 5: Delivery Process Chart
BOARD AGENDA MEMORANDUM


SUBJECT:
Title
Notice of Completion of Contract and Acceptance of Work for the Lower Silver Creek Flood Protection and Creek Restoration Project, Reaches 5C to 6A (Construction Phase - Milestone 1), Proven Management, Inc., Contractor, Project No. 40264008, Contract No. C0580 (San Jose) (District 6).


End
RECOMMENDATION:
Recommendation
A. Accept the work as complete; and
B. Direct the Clerk of the Board to sign the Notice of Completion of Contract and Acceptance of Work and submit for recording to the Santa Clara County Clerk-Recorder.


Body
SUMMARY:
The construction contractor, Proven Management, Inc., has completed the Construction Phase (Milestone 1) for the Lower Silver Creek Flood Protection and Creek Restoration Project, Reaches 5C to 6A (Project). The construction contract was awarded in the amount of $18,217,915.50 and the contract amount through the completion of Milestone 1 is $20,945,274.93. Subject to any withholds required by law or the contract, acceptance of the work by the Board will allow for the release of approximately $1,024,390 in retention to the contractor.

The objective of the Lower Silver Creek Flood Protection and Creek Restoration Project, Reaches 5C to 6A (Project) is to convey the 1 percent flood flows and improve stream habitat values. The Project reach extends approximately 2,000 feet between Story Road and Moss Point Drive. This Project is the second segment of the Lower Silver Creek, Reaches 4-6 Project that the District is constructing in partnership with the Natural Resources Conservation Service. The District has received $20.2 million for the Reaches 4-6 Project from a federal grant as part of the American Recovery and Reinvestment Act of 2009 to construct improvements along 2.3 miles of the creek. Completion of the Reaches 5C to 6A Project, together with future improvements planned by the District's Lake Cunningham project, will provide flood protection for a total of 3,800 parcels in the s...

Click here for full text



Notice to Public:

The Santa Clara Valley Water District publishes meeting agendas two Fridays prior to regular meetings, and publishes amended and special meeting agendas one Friday prior. During the process of amending an agenda, individual links to Board Agenda Reports may not be available. In these cases, please reference the “Full Agenda Package” instead.