File #: 18-0090    Version: 1 Name:
Type: Water Utility Enterprise Item Status: Agenda Ready
File created: 2/1/2018 In control: Board of Directors
On agenda: 5/8/2018 Final action:
Title: Budget Adjustment in the Amount of $5 Million from the Rinconada Water Treatment Plant Residuals Management Project to the Rinconada Water Treatment Plant Residuals Remediation Project, Project No. 93294058; and Standard Consultant Agreement between the Santa Clara Valley Water District and Stantec Consulting Services, Inc., for Project Planning and Design Services (Los Gatos) (District 7).
Attachments: 1. Attachment 1: Consultant Agreement
BOARD AGENDA MEMORANDUM


SUBJECT:
Title
Budget Adjustment in the Amount of $5 Million from the Rinconada Water Treatment Plant Residuals Management Project to the Rinconada Water Treatment Plant Residuals Remediation Project, Project No. 93294058; and Standard Consultant Agreement between the Santa Clara Valley Water District and Stantec Consulting Services, Inc., for Project Planning and Design Services (Los Gatos) (District 7).


End
RECOMMENDATION:
Recommendation
A. Approve a budget adjustment of $5 million from the Rinconada Water Treatment Plant Residuals Management Project, Project No. 93294051, to the Rinconada Water Treatment Plant Residuals Remediation Project, Project No. 93294058, to fund project expenditures for Fiscal Years 2018 and 2019; and
B. Approve the Standard Consultant Agreement Between the Santa Clara Valley Water District and Stantec Consulting Services, Inc., for project planning and design services, for a not-to-exceed fee of $3,296,795.


Body
SUMMARY:
The Rinconada Water Treatment Plant (RWTP) residual solids management facility has experienced numerous operational deficiencies since construction completion in 2016 of the RWTP Residuals Management Project. It has been determined that the new residuals management system does not meet the District's objectives and requirements and is not reliable.

Staff has completed a consultant selection process for services to identify and permanently address the operational deficiencies. Staff recommends a budget adjustment of $5.0 million to fund a new project established to create a clear accounting record of remediation costs for the residuals management system. The new project is the RWTP Residuals Remediation Project (Project No. 93294058).

Staff also recommends approval of a Consultant Agreement with Stantec Consulting Services, Inc. (Consultant) for remediation planning and design services, for a not-to-exceed fee of $3,296,795.

Project Background
The RWTP is the only source of t...

Click here for full text



Notice to Public:

The Santa Clara Valley Water District publishes meeting agendas two Fridays prior to regular meetings, and publishes amended and special meeting agendas one Friday prior. During the process of amending an agenda, individual links to Board Agenda Reports may not be available. In these cases, please reference the “Full Agenda Package” instead.