File #: 19-0950    Version: 1 Name:
Type: Consent Calendar Item Status: Agenda Ready
File created: 9/30/2019 In control: Board of Directors
On agenda: 2/11/2020 Final action:
Title: Receive and Direct the Clerk to File the Notice of Completion of Contract and Acceptance of Work for the Uvas Creek Levee Rehabilitation Project Phase 2 (Construction Stage 1 - Milestones 1, 2 and 3), Odin Construction Solutions, Inc., Contractor, Project No. 62084001, Contract No. C0648 (Gilroy, District 1).
Attachments: 1. Attachment 1: Notice Completion/Acceptance of Work, 2. Attachment 2: Contractor Project Milestone Completion Letter, 3. Attachment 3: Project Completion Letter, 4. Attachment 4: Construction Contract Acceptance, 5. Attachment 5: Construction Summary, 6. Attachment 6: Project Delivery Process Chart
BOARD AGENDA MEMORANDUM


SUBJECT:
Title
Receive and Direct the Clerk to File the Notice of Completion of Contract and Acceptance of Work for the Uvas Creek Levee Rehabilitation Project Phase 2 (Construction Stage 1 - Milestones 1, 2 and 3), Odin Construction Solutions, Inc., Contractor, Project No. 62084001, Contract No. C0648 (Gilroy, District 1).



End
RECOMMENDATION:
Recommendation
A. Accept the Work on the Uvas Creek Levee Rehabilitation Project Phase 2 (Construction Stage 1 - Milestones 1, 2 and 3), Project No. 62084001, Contract No. C0648 as complete; and
B. Direct the Clerk of the Board to sign the Notice of Completion of Contract and Acceptance of Work for Uvas Creek Levee Rehabilitation Project Phase 2 (Construction Stage 1 - Milestones 1, 2 and 3) and submit for recording at the Santa Clara County Clerk-Recorder.


Body
SUMMARY:
The Construction Contractor, Odin Construction Solutions, Inc. (Odin), has completed Construction Stage 1 (Milestones 1, 2 and 3)* for the Uvas Creek Levee Rehabilitation Project Phase 2 (Project). On May 28, 2019, the Board awarded the construction contract in the amount of $3,754,817 and approved a 10% contingency of $375,482.

*Milestones 1, 2 and 3 include completing all required civil construction components of the project, including levee embankment reconstruction, chain link fabric installation over the finished slopes, restoration of the asphalt concrete trail, and hydroseeding of the finished slopes and constructed impacted areas.

Construction Stage 1 of the Project was completed on November 25, 2019 and the final contract amount incurred for Construction Stage 1 is $3,347,543. Subject to any withholds required by law or the contract, acceptance of the work by the Board will allow for the release of $167,377 in retention to the Contractor.

Construction Stage 2 of the Project consists of the three-year planting establishment period and maintenance work of the Contract (Milestone 4), which commenced on Novembe...

Click here for full text



Notice to Public:

The Santa Clara Valley Water District publishes meeting agendas two Fridays prior to regular meetings, and publishes amended and special meeting agendas one Friday prior. During the process of amending an agenda, individual links to Board Agenda Reports may not be available. In these cases, please reference the “Full Agenda Package” instead.