BOARD AGENDA MEMORANDUM
SUBJECT:
Title
Receive and Direct the Clerk to File the Notice of Completion of Contract and Acceptance of Work for the Lower Silver Creek Flood Protection and Creek Restoration Project, Reach 6B (Landscape and Revegetation Establishment Maintenance Phase - Milestone 2), Robert A. Bothman, Inc., Contractor, Project No. 40264008, Contract No. C0594 (San Jose) (District 6).
End
RECOMMENDATION:
Recommendation
A. Accept the work on the Lower Silver Creek Flood Protection and Creek Restoration Project, Reach 6B (Landscape and Revegetation Establishment Maintenance Phase - Milestone 2), Robert A. Bothman, Inc., Contractor, Project No. 40264008, Contract No. C0594 as complete; and
B. Direct the Clerk of the Board to sign the Notice of Completion of Contract and Acceptance of Work and submit for recording to the Santa Clara County Clerk-Recorder.
Body
SUMMARY:
The construction contractor, Robert A. Bothman, Inc., has completed the Landscape and Revegetation Establishment Maintenance Phase (Milestone 2) for the Lower Silver Creek Flood Protection and Creek Restoration Project, Reach 6B. The construction contract was awarded in the amount of $12,677,594 and the final contract amount is $12,997,848.15. Subject to any withholds required by law or the contract, acceptance of the work by the Board will allow for the release of approximately $8,925 in retention to the Contractor.
The objective of the Lower Silver Creek Flood Protection and Creek Restoration Project, Reach 6B (Project) is to convey the one percent chance flood flows and improve stream habitat values. The Project reach extends approximately 2,750 feet between Moss Point Drive and Cunningham Avenue. This Project is the final segment of the Lower Silver Creek, Reaches 4-6 Project that Valley Water is constructing in partnership with the Natural Resources Conservation Service. Valley Water has received $20.2 million for the Reaches 4-6 Project from a federal grant as part of the...