BOARD AGENDA MEMORANDUM
SUBJECT:
Title
Monitoring and Assessment Program Evaluation of Los Vaqueros Reservoir Expansion, Sites Reservoir, and Delta Conveyance Project.
End
RECOMMENDATION:
Recommendation
A. Receive and discuss information regarding the Los Vaqueros Reservoir Expansion Project, Sites Reservoir Project, and Delta Conveyance Project;
B. Authorize the Chief Executive Officer (CEO) to execute Amendment 2 to the 2019 Multi-Party Agreement for Los Vaqueros Reservoir Expansion Project, which includes a contract extension through December 2021 and a cost-share not to exceed $1,013,661;
C. Authorize the CEO to execute the Second Amendment to 2019 Reservoir Project Agreement with Sites Project Authority and the Project Agreement Members for a participation level of 0.2 percent with a $50,000 cost share; and
D. For the Delta Conveyance Project:
i. Approve a provisional participation percentage in the Project of 2.73 percent and authorize the CEO to increase Valley Water's provisional participation percentage up to a total of 3.23 percent if additional shares become available;
ii. Adopt the Resolution APPROVAL OF PROVISIONAL PARTICIPATION PERCENTAGE AND AUTHORIZING NEGOTIATION AND EXECUTION OF A FUNDING AGREEMENT FOR PRELIMINARY PLANNING AND DESIGN COSTS RELATED TO A POTENTIAL DELTA CONVEYANCE PROJECT;
iii. Authorize the CEO to negotiate and execute a funding agreement with the Department of Water Resources committing up to $4,034,001 for Project environmental planning and design costs incurred in Calendar Years 2021 and 2022, with an option to commit up to an additional $6,972,348, upon future approval of the Board, for Project environmental planning and design costs incurred in Calendar Years 2023 and 2024; and
iv. Approve and Authorize the CEO to execute the Amended and Restated Joint Powers Agreement Forming the Delta Conveyance Design and Construction Authority.
Body
SUMMARY:
The Water Supply Master Plan 2040 (Master Plan) is Santa Clara V...