File #: 20-1095    Version: 2 Name:
Type: Watersheds Item Status: Agenda Ready
File created: 11/19/2020 In control: Board of Directors
On agenda: 1/12/2021 Final action:
Title: Approve a Budget Adjustment in the Amount of $3,886,677 and Authorize the Chief Executive Officer to Negotiate and Execute Amendments to Consultant Agreements A4170G, for Native American Consulting Services for Permanente Creek Flood Protection Project, with Andrew Galvan, and A3932A, for Permanente Creek Flood Protection Project - Rancho San Antonio Construction Management Services, with Harris & Associates, Project No. 26244001, Rancho San Antonio Detention Basin Project. (Cupertino) (Districts 5 and 7).
Attachments: 1. Board Agenda Memo, 2. Board Agenda Memo
BOARD AGENDA MEMORANDUM


SUBJECT: Title
Approve a Budget Adjustment in the Amount of $3,886,677 and Authorize the Chief Executive Officer to Negotiate and Execute Amendments to Consultant Agreements A4170G, for Native American Consulting Services for Permanente Creek Flood Protection Project, with Andrew Galvan, and A3932A, for Permanente Creek Flood Protection Project - Rancho San Antonio Construction Management Services, with Harris & Associates, Project No. 26244001, Rancho San Antonio Detention Basin Project. (Cupertino) (Districts 5 and 7).


End
RECOMMENDATION: Recommendation
A. Approve a budget adjustment of $3,886,677 from Fund 26 Operating and Capital Reserves to the Permanente Creek Flood Protection Project;
B. Authorize the Chief Executive Officer to negotiate and execute Amendment No. 2 to Agreement A4170G, for Native American Consulting Services for Permanente Creek Flood Protection Project, with Andrew Galvan, to provide Native American monitoring; and
C. Authorize the Chief Executive Officer to negotiate and execute Amendment No. 4 to Agreement No. A3932A, for Permanente Creek Flood Protection Project - Rancho San Antonio Construction Management Services, with Harris & Associates, to provide construction management services for the Permanente Creek Project, Rancho San Antonio Detention Basin Project.


Body
SUMMARY:
The Permanente Creek Flood Protection Project (Project) is included in the Safe, Clean Water and Natural Flood Protection Program (Safe, Clean Water Program). This Project protects approximately 2,200 parcels by implementing flood detention and channel improvements. The Project utilizes two flood detention areas located strategically in the watershed to maximize flood protection benefits while minimizing the construction work required in the downstream urban areas of the creek. The Project is being constructed through three separately bid sub-projects: Rancho San Antonio Detention Basin (RSA Project); McKelvey Park Detention Basin...

Click here for full text



Notice to Public:

The Santa Clara Valley Water District publishes meeting agendas two Fridays prior to regular meetings, and publishes amended and special meeting agendas one Friday prior. During the process of amending an agenda, individual links to Board Agenda Reports may not be available. In these cases, please reference the “Full Agenda Package” instead.