File #: 20-1148    Version: 1 Name:
Type: Water Utility Enterprise Item Status: Agenda Ready
File created: 12/4/2020 In control: Board of Directors
On agenda: 1/12/2021 Final action:
Title: Notice of Completion of Contract and Acceptance of Work for the Rinconada Water Treatment Plant Reliability Improvement Project, Balfour Beatty Infrastructure, Inc., Contractor, Project No. 93294057, Contract No. C0601 (Los Gatos) (District 7). (Continued from November 10, 2020) (PREVIOUSLY LISTED AS ITEM 5.1)
Attachments: 1. Attachment 1: SCVWD BOD 111020 Item 3.1, 2. Attachment 2: Stop Payment Notice Log, 3. Attachment 3: Notice of Completion/Acceptance of Work, 4. *Handout 3.16-A: Neal Electric Corp., 5. *Handout 3.16-B: Farwest Insulation Contracting, 6. Board Agenda Memo, 7. Board Agenda Memo
BOARD AGENDA MEMORANDUM


SUBJECT:
Title
Notice of Completion of Contract and Acceptance of Work for the Rinconada Water Treatment Plant Reliability Improvement Project, Balfour Beatty Infrastructure, Inc., Contractor, Project No. 93294057, Contract No. C0601 (Los Gatos) (District 7). (Continued from November 10, 2020) (PREVIOUSLY LISTED AS ITEM 5.1)


End
RECOMMENDATION:
Recommendation
A. Accept the work on the Rinconada Water Treatment Plant Reliability Improvement Project, Project No. 93294057, Contract No. C0601 as complete; and
B. Direct the Clerk of the Board to sign the Notice of Completion of Contract and Acceptance of Work and submit for recording to the Santa Clara County Clerk-Recorder.


Body
SUMMARY:
The Construction Contractor, Balfour Beatty Infrastructure, Inc., has completed the Rinconada Water Treatment Plant Reliability Improvement Project (Project). The construction contract was awarded in the amount of $179,850,000 and the final contract amount is $152,803,135.72. Subject to any withholds required by law or the contract, acceptance of the work by the Board will allow for the release of $7,640,156.78 in retention to the contractor.

Project Background

On May 26, 2015, the Board awarded a construction contract (Contract) in the amount of $179,850,000 to Balfour Beatty Infrastructure, Inc. (BBII) for the Rinconada Water Treatment Plant Reliability Improvement Project (Project). The Contract provided for the Project to be constructed in five primary phases within a 5-year period, with a final sixth phase consisting of site restoration and contract closeout. The existing Rinconada Water Treatment Plant (RWTP) was to remain operational during the entire construction period, with the newly-constructed facilities and upgrades integrated with plant operations at the end of each phase.

Phase 1 of the work included activities to prepare the site for construction, including traffic control, installation of temporary construction facilit...

Click here for full text



Notice to Public:

The Santa Clara Valley Water District publishes meeting agendas two Fridays prior to regular meetings, and publishes amended and special meeting agendas one Friday prior. During the process of amending an agenda, individual links to Board Agenda Reports may not be available. In these cases, please reference the “Full Agenda Package” instead.