Skip to main content
File #: 25-0340    Version: 1 Name:
Type: Assistant CEO Item Status: Agenda Ready
File created: 3/26/2025 In control: Board of Directors
On agenda: 6/10/2025 Final action:
Title: Receive an Update on the Anderson Dam Tunnel Project.
Attachments: 1. Attachment 1: PowerPoint

BOARD AGENDA MEMORANDUM

 

Government Code § 84308 Applies:  Yes    No 
(If “YES” Complete Attachment A - Gov. Code § 84308)

 

SUBJECT:

Title

Receive an Update on the Anderson Dam Tunnel Project.

 

 

End

RECOMMENDATION:

Recommendation

Receive an Update on the Anderson Dam Tunnel Project.

 

 

Body

SUMMARY:

 

Background

 

The Anderson Dam Tunnel Project (ADTP), Project No. 91864006, is currently being constructed and includes building a diversion system to augment the existing outlet, consisting of a new diversion tunnel, an outlet structure, a micro-tunnel lake tap, and modifications to Coyote Creek just downstream of the base of the dam. Once completed, the ADTP will serve as the Stage 1 Diversion System to divert inflows from the reservoir to Coyote Creek during the beginning of the Anderson Dam Seismic Retrofit Project (ADSRP). All of the ADTP elements, except for the micro-tunnel lake tap portion, will be incorporated into the final configuration of the ADSRP.

 

On April 27, 2021, Valley Water’s Board of Directors awarded the construction contract for the ADTP to the top-ranked best-value proposer, Flatiron West, Inc. (Contractor), in the sum of $161,140,321 and approved a contingency amount of $40,000,000 (25% of the contract price).

 

On January 28, 2025, the Board of Directors approved an increase of $40,000,000 to the construction contract contingency sum, bringing the total construction contract contingency to $80,000,000.

 

Project Construction

 

Several major elements of the ADTP construction have been completed to date, including:

 

                     Tunnel Excavation and Initial Lining

Tunnel excavation and initial lining of the tunnel were completed in April 2024. The Contractor used conventional mining methods, including drilling and blasting the rock to complete the excavation. The initial lining installed to support the excavation consists of an 8-inch thick layer of fiber-reinforced shotcrete (spray-applied concrete) and steel support arches spaced every 3 to 5 feet.

 

                     Microtunnel and Lake Tap

Conclusion of tunneling and tapping into the reservoir was completed in August 2024. A micro-tunnel boring machine (MTBM) drilled through the last 350 feet of tunnel into the reservoir about 30 feet under the water surface. Sections of 8-foot diameter steel pipe were driven into the ground behind the MTBM in this portion of the tunnel.

 

                     Diversion Outlet Structure (DOS) Construction

Construction of the DOS outside the downstream tunnel portal was completed in June 2024. The DOS will be used to house the two large fixed-cone valves that control flows through the tunnel and dissipate the energy of the releases by reducing the velocity of the water. The foundation, walls, and roof of the structure are made of thick, reinforced concrete sections that were placed in multiple stages.

 

                     North Channel Extension

Work to reopen the North Channel was completed in November 2024. The work included excavation, grading, and rock placement for over 1,600 linear feet starting outside the DOS to reconnect this historic creek channel back to Coyote Creek. A concrete labyrinth weir was also installed in the channel to dissipate the energy and control high flows to be released from Anderson Reservoir.

 

The remaining major construction elements to be completed include:

 

                     South Channel Weir Construction

Improvement of the South Channel by constructing a new concrete weir, with a notch for low-flow passage. This weir will work in conjunction with the North Channel Weir to control flow releases from Anderson Reservoir in this reach of Coyote Creek.

 

                     Final Tunnel Lining Installation

Construction of the final tunnel lining. There are three distinct structural systems that will be used for the final tunnel lining:

o                     Continuous Reinforced Concrete - a 24-inch thick, horseshoe-shaped arch, walls, and floor

o                     Articulating Joint Concrete Sections - a similar 24-inch thick reinforced concrete structure with heavier reinforcement and gaps between sections every five or ten feet designed to independently displace if ground movements occur.

o                     Steel Pipe with Concrete Backfill - about 450 linear feet of 13-foot diameter steel pipe will be installed at the downstream end of the tunnel that exits the portal. The annular space will be backfilled with concrete.

 

                     Diversion Outlet Structure (DOS) Large Diameter Pipe and Valve Installation

Installation of the large diameter steel pipes and valves in the DOS. As the 13-foot diameter steel pipe exits the tunnel, it bifurcates into two 11-foot diameter steel pipes. Each of the 11-foot diameter pipes have a butterfly valve and fixed cone valve to control flow releases and dissipate energy into the DOS.

 

 

Project Schedule

 

The ADSRP FERC Order received in February 2020 stated that Valley Water should advance the low-level outlet tunnel portion of the project immediately as a risk reduction measure. The project team advanced the design for the tunnel as a separate package for construction. When the ADTP contract was awarded, several permits and design elements had not been fully approved. This decision was consistent with the need to build the tunnel as soon as possible.

 

Due to the delay in notice to proceed based on final permits and design changes through final review by various regulatory agencies, the ADTP has experienced several delays resulting in contract time extensions. Some additional design changes occurred during construction based on differing site conditions and resulted in substantial project delays as well.

 

Table 1 below summarizes each time extension which included a time impact analysis of the project schedule.

 

Table 1 - Project Schedule Extensions and Completion Dates

 

 Time Impact Analysis (TIA)

Contract time extension in calendar days

Construction Contract Completion Date

Original Contract Completion Date (Start 6/28/2021)

-

3/4/2024

TIA-01 (Delay to issue Notice to Proceed 2A)

79

5/15/2024

TIA-02 (HLOW Drop  Shaft design changes)

166

11/4/2024

TIA-03 (Diversion Outlet Structure excavation design changes)

56

12/30/2024

TIA-04 (Tunnel Excavation differing site conditions)

25

1/24/2025

TIA-05 (North Channel design changes)

236

9/17/2025

TIA-06 (Tunnel Final Lining Changes)

443

12/4/2026

Total

1,005

 

 

 

Project Cost

There have been several changes to the construction contract cost due to various reasons. Many of the cost increases are associated with the contract time extensions summarized above. When the duration of the contract is extended by changes directed by Valley Water or differing site conditions, the Contractor can claim additional overhead costs and other additional charges for the extended contract time. There have also been other differing site conditions related to the dredging, overruns on certain bid item unit quantities, and design changes to improve compatibility with the ADSRP. Significant credits have been applied to the total contract amount as well due to design changes that reduced the scope of work for the Contractor. All cost changes have been presented as Contract Change Orders throughout the life of the ADTP. Table 2 below summarizes the current construction contract cost and amount billed to date (through April 2025 billing).

Table 2 - ADTP Construction Contract Amount and Remaining Balance

  

Contract Amount

Total Billed

Balance Remaining

Original Contract

$ 161,140,321

$ 125,911,004

$ 35,229,317

Change Orders (includes Pending)

$ 58,355,786

$ 27,673,312

$ 30,682,474

Total Contract

$ 219,496,107

$ 153,584,316

$ 65,911,791

 

The original contract cost contingency of $40,000,000 was established when the contract was awarded. After several cost increases and schedule extensions, Staff recommended an increase to the contract cost contingency for a total of $80,000,000 which the Board of Directors approved as noted above in the Background section. Based on Contract Change Orders executed and pending to date totaling $58,355,786, the remaining contract contingency is $21,644,214. There are additional anticipated cost changes that will reduce the remaining contingency once finalized.

 

 

ENVIRONMENTAL JUSTICE IMPACT:

There are no Environmental Justice impacts associated with this item. However, the Environmental Justice Impacts of the Project will be assessed and addressed in future Project board actions related to the Project execution.

 

 

FINANCIAL IMPACT:

The Anderson Dam Tunnel Project (ADTP), Project No. 91864006, is included in the Capital Improvement Program (CIP) Fiscal Years (FY) 2025-29 Five-Year Plan. There are no financial impacts associated with this item.

 

 

CEQA:

The recommended action does not constitute a project under CEQA because it does not have the potential to result in a direct or reasonably foreseeable indirect physical change in the environment.

 

 

ATTACHMENTS:

Attachment 1: PowerPoint

 

 

UNCLASSIFIED MANAGER:

Manager

Ryan McCarter, 408-630-2983




Notice to Public:

The Santa Clara Valley Water District publishes meeting agendas two Fridays prior to regular meetings, and publishes amended and special meeting agendas one Friday prior. During the process of amending an agenda, individual links to Board Agenda Reports may not be available. In these cases, please reference the “Full Agenda Package” instead.