File #: 16-0661    Version: 1 Name:
Type: Watersheds Item Status: Agenda Ready
File created: 7/20/2016 In control: Board of Directors
On agenda: 9/27/2016 Final action:
Title: Fiscal Year 2015-2016 (FY15-16) Safe, Clean Water and Natural Flood Protection Program Annual Report - Year 3 (County-wide).
Attachments: 1. Attachment 1: FY16 SCW Annual Report, 2. Attachment 2: PowerPoint

BOARD AGENDA MEMORANDUM

 

 

SUBJECT:

Title

Fiscal Year 2015-2016 (FY15-16) Safe, Clean Water and Natural Flood Protection Program Annual Report - Year 3 (County-wide).

 

 

End

RECOMMENDATION:

Recommendation

A.                     Approve the proposed text adjustments to the Safe, Clean Water and Natural Flood Protection (Safe, Clean Water) Program;  

B.                     Approve the FY15-16 Safe, Clean Water Program Annual Report - Year 3 with unaudited financials; and 

C.                     Authorize staff to finalize the FY15-16 Safe, Clean Water Program Annual Report - Year 3 Annual Report (with audited financials) and submit the final report to the Independent Monitoring Committee (IMC) for its review.

 

 

Body

SUMMARY:

Safe, Clean Water Program Text Adjustments

 

As per the Safe, Clean Water Program’s Change Control Process, the proposed text adjustments are listed below and incorporated into the Year 3 annual report. Adjustments to project schedules and budgets are approved annually through the Capital Improvement Program Progress Report and Budget Adjustment and Adoption processes, respectively.

                     

                     A1 Main and Madrone Avenue Pipelines Restoration

                     Section: Description

Adjusted text:

This project will restore the Main Avenue and Madrone pipelines to full operating capacity of 37 cubic feet per second from Anderson Reservoir. The upgrade includes replacement of a 1-mile section of pipe on the Main Avenue line which has been out of service since 1994, and restoration of approximately 1.25 miles of Madrone pipeline which has restricted capacity due to root intrusion and deterioration. conveying 10 cubic feet per second (cfs) and 27 cfs, respectively, for a total of 37 cfs from Anderson Reservoir or the Santa Clara Conduit for groundwater recharge via the Main Avenue Recharge Ponds and the Madrone Channel. The project will plan, design, and construct approximately 14,000 linear feet or 2.6 miles of 30-inch to 36-inch diameter pipeline and associated appurtenances.

                     Justification:                     

An adjustment to the project description is necessary to reflect the results of the planning-level hydraulic analysis that was completed during the 30% design. The analysis recommended that an additional 5000 feet of pipeline replacement was needed to meet future recharge volumes.

                     

 

                     B4 Good Neighbor Program: Illegal Encampment Cleanup

                     Section: Title and Description

                     Adjusted text:

                     Good Neighbor Program: Illegal Encampment Cleanup

This project supports the District’s ongoing coordination with local cities and agencies to clean up large illegal creekside encampments that contaminate waterways and damage District facilities. This cooperative effort includes local police departments, social services, and nonprofit advocacy groups that help provide alternatives to homelessness.

                     Justification:

                     The adjustment to the title was requested by members of the Board.

 

                     D4 Fish Habitat and Passage Improvement

                     Section: Benefit

                     Adjusted text:

Helps provide required mitigation for environmental impacts of reservoir and recharge operations and for countywide Stream Maintenance Program

                     Justification:

The adjustment to the benefit reflects the benefits provided through implementation of the project.

 

                     E2 Emergency Response Planning

                     Section: Description

                     Adjusted text:

This project allows the District to work with local municipalities to clearly identify roles and responsibilities for floodplain management and flood emergency management. The project supports countywide emergency response and preparedness activities, and develops communication procedures and disseminates web-based flood forecasting information developed under Priority C2, Emergency Response Upgrades. Collaborators also develop formal, site-specific flood-fighting strategies and coordinate outreach throughout the county so that the public receives uniform flood warning messages.

                     Justification:

                     The adjustment to the description improves readability.

 

The following list of projects have had minor grammatical changes made to their benefits sections to bring the text from future tense to present tense:

 

B1 Impaired Water Bodies Improvement

B2 Interagency Urban Runoff Program

                     B3 Pollution Prevention Partnerships and Grants

                     B5 Hazardous Materials Management and Response

                     B6 Good Neighbor Program: Graffiti and Litter

                     B7 Support Volunteer Cleanup Efforts and Education

                     C1 Anderson Dam Seismic Retrofit

                     C2 Emergency Response Upgrade

                     D2 Revitalize, Upland and Wetland Habitat

                     D3 Grants and Partnerships to Restore Wildlife Habitat and Provide Access to Trails

                     D4 Fish Habitat and Passage Improvement

                     D5 Ecological Data Collection and Analysis

                     D6 Creek Restoration and Stabilization

                     D7 Partnerships for the Conservation of Habitat Lands

                     D8 South Bay Salt Ponds Restoration Partnership

                     E1 Vegetation Control and Sediment Removal for Flood Protection

                     E2 Emergency Response Planning

                     E3 Flood Risk Reduction Studies

                     E4 Upper Penitencia Creek Flood Protection Coyote Creek to Dorel Drive - San José

E5 San Francisquito Creek Flood Protection San Francisco Bay to Middlefield Road - Palo Alto

E6 Upper Llagas Creek Flood Protection Project Buena Vista Avenue to Wright Avenue - Morgan Hill, San Martin Gilroy

E7 San Francisco Bay Shoreline Study Milpitas, Mountain View, Palo Alto, San José, Santa Clara and Sunnyvale

 

 

Fiscal Year 2015-2016 Safe, Clean Water Program Annual Report - Year 3

 

FY16 marks the third year of the 15-year Safe, Clean Water and Natural Flood Protection Program (Safe, Clean Water). This report (Year 3 annual report) presents a status update on the implementation of projects during FY16.

 

On November 6, 2012, voters approved the Safe, Clean Water program as a countywide special parcel tax for 15 years with a sunset date of June 30, 2028. This program replaced the Clean, Safe Creeks and Natural Flood Protection Program, which voters approved in November 2000. The Safe, Clean Water program addresses the following needs, values, and priorities as identified by Santa Clara County stakeholders:

 

Priority A: Ensure a safe, reliable water supply

Priority B: Reduce toxins, hazards and contaminants in our waterways

Priority C: Protect our water supply from earthquakes and natural disasters

Priority D: Restore wildlife habitat and provide open space

Priority E: Provide flood protection to homes, businesses, schools, and highways

 

Each of these priorities has specific operational and capital projects, which have key performance indicators (KPIs) meant to keep them on track to meet the overall program priorities. Additionally, the program requires the District to prepare an annual report providing a progress update and fiscal year accomplishments for each project. Also, to ensure transparency and accountability, the program requires that the annual report be reviewed by an Independent Monitoring Committee (IMC) of volunteers appointed by the District Board of Directors (Board).

 

The report provides the status of each project’s progress towards accomplishing its KPIs and targets established in the 5-Year Implementation Plan. The project status is described by one of five categories listed on the following page:

On Target: Status indicates the project is on track to meet targets

Adjusted: Status indicates the potential that targets will not be met and implementation required adjustment (future year status’ will be based upon the adjusted project targets)

Not on Target: Status indicates that the target has not been or will not be met

Modified: Status indicates the Board formally modified the project following a public hearing (future year status’ will be based upon the modified project targets)

Scheduled to Start: Status indicates that the project is scheduled to start in a future fiscal year

Completed: Status indicates that the project has been completed and the KPIs have been met

 

Overall FY16 Program Performance

 

There are 38 projects under Safe, Clean Water. As of June 30, 2016, 74%, or 28 projects, are on target, 21% (8 projects) required schedule adjustments; 2.5% or 1 project is not scheduled to start until Fiscal Year 2025; and 2.5% or 1 project was completed and closed out (Graph 1). The table on the following page summarizes total program status as of June 30, 2016.

Graph 1

 

(See “Table 1: Program Status as of June 30, 2016” on following page.)

For FY16, the adopted budget for the program totaled $149 million. Actual funds expended and encumbered as of June 30, 2016 were $82.9 million, approximately 56% of the Safe, Clean Water Program’s adopted budget. Underspending was primarily due to delays in construction of the following capital flood protection projects: Upper Llagas (E6), Permanente Creek (CSC), and Sunnyvale East & West (CSC). Project construction delays occurred primarily as a result of: addressing redesign or analyses requested by regulatory agencies, delays in acquisition of regulatory permits, and delays in land acquisition. To address delays in obtaining permits, the District permit strategy team continues to work on short and long-term strategies to secure timely permits.

 

To address recommendations made by the IMC, the District has introduced a confidence level rating system for capital projects that include confidence levels for schedule, funding, permits, and when applicable, jurisdictional complexity (the level to which a project’s deliverables can be impacted by other entities or jurisdictions). By applying a confidence level to each of these topics, the IMC and community will be able to identify the areas of concern for each project that could impact the probability for the project to remain On Target. The confidence levels are addressed under the Opportunities and Challenges section for each of the capital projects. Listed below are the 3 confidence levels and their definitions:

 

High - Applies to projects that have achieved the following: received full funding, received regulatory permits, met schedule milestones (and will continue to move forward on schedule), and, if applicable, jurisdictional complexity issues have been resolved.

 

Moderate - Applies to projects that are in the process of the following: receiving funding from other sources, receiving permits, requesting the Board approve a schedule adjustment, and, if applicable, resolving jurisdictional complexity issues.

 

Low - Applies to projects that have a high probability of experiencing or already have been: denied funding, denied permits, delayed in schedule, and, if applicable, jurisdictional complexity issues that are impacting completion of the project.

 

Key Accomplishments

 

Some highlights of the Program in the third year are:

 

                     Fish Habitat and Passage Improvement (Evelyn Bridge): District completed construction of the Evelyn Bridge Fish Passage project at Stevens Creek on November 21, 2015. The Evelyn Bridge Fish Passage Project provides mitigation credit for maintenance work that will be conducted for flood control under the District’s Countywide Stream Maintenance Program.

                     San Francisquito Creek Flood Protection Project: Board awarded the construction contract for the San Francisco Bay to Highway 101 Flood Protection project.

                     San Francisco Bay Shoreline Study: Study partners held a successful U.S. Army Corps of Engineers (USACE) Civil Works Review Board for the urban area of North San Jose/Alviso/San Jose-Santa Clara Regional Wastewater Facility Environmental Impact Area (EIA 11) on September 11, 2015, the USACE Chief’s Report was signed by December 2015, and the Environmental Impact Report was certified by the Board in March 2016. Achieving these milestones allowed the study partners to close out the feasibility study phase in FY16 and to move forward with the preliminary engineering and design phase in FY17.

                     Upper Guadalupe River Flood Protection Project: USACE completed the channel construction for Reach 12 (from Branham Lane to Blossom Hill Road) in November 2015.

                     Water Conservation Grants: Board awarded $130,000 to 3 recipients to test new conservation activities. Total amount awarded since FY14 is $458,500.

                     Safe, Clean Water Cleanup Activities: District removed a total of more than 937 tons (approximately 13,118 cubic yards) of trash and debris from our waterways through pollution prevention and reduction activities, trash capture devices, encampment cleanups, trash and debris removal, and volunteer cleanup programs and events (projects B1, B2, B4, B6, and B7 respectively).

                     Emergency Response Upgrades: District partnered with Colorado State University and National Oceanic and Atmospheric Administration on a pilot project using X-Band Doppler radar to improve forecasting rainfall amount. In addition, the District added flood forecast systems for Uvas Creek and Lower Silver Creek. Together with the West Little Llagas Creek, Upper Guadalupe River and San Francisquito Creek systems, 5 of the 7 required flood-warning systems are now complete.

                     Grants and Partnerships to Restore Wildlife Habitat and Provide Access to Trails: Board awarded 17 grants totaling $1,988,684, in FY16 to restore wildlife habitat. In addition, the Board approved a pilot mini-grant program, to be implemented in FY17, designed to provide seed funding to encourage broader and long-term community engagement in wildlife habitat restoration or watershed stewardship activities in Santa Clara County.

                     Safe, Clean Water Change Control Process: Board approved the Safe, Clean Water Change Control Process, which established the processes for adjustments, modifications and project non-implementation for the Safe, Clean Water Program.

 

5-Year Implementation Plan

On May 14, 2013, the Board approved a 5-Year Implementation Plan that describes how the District will effectively and efficiently implement the program over the first five years of the 15-year Safe Clean Water Program. The annual report will provide stakeholders the opportunity to compare the program’s third-year performance with the targeted accomplishments in the 5-Year Implementation Plan.

 

Next Steps

 

Once approved by the Board and finalized, the report will be sent to the IMC and made available to the public on the District’s website at www.valleywater.org/SafeCleanWater.aspx <http://www.valleywater.org/SafeCleanWater.aspx>.

 

The IMC is scheduled to receive the final report by November 18, 2016, after which time the committee will reconvene in the first week of December to discuss and establish the review process and schedule for the FY16 annual report. Also during that meeting, the committee will receive presentations on the following projects:

A2 - Nitrate Treatment System Rebate Program, including detailed outreach information to well users;

B1 - Trash map presentation; and

D2 - Presentation on plant palettes and possible users.

 

In addition, staff will provide a report on the Board Ad Hoc committee outcomes focused on addressing needs of the homeless and the impacts to the rivers and creeks.

 

 

FINANCIAL IMPACT:

The annual report is produced and printed internally and budgeted to the Safe, Clean Water Implementation Project (26061012).

 

 

CEQA:

The recommended action does not constitute a project under CEQA because it does not have a potential for resulting in direct or reasonably foreseeable indirect physical change in the environment.

 

 

ATTACHMENTS:

Attachment 1:  FY16 Safe, Clean Water Annual Report

Attachment 2:  PowerPoint

 

 

UNCLASSIFIED MANAGER:

Manager

Ngoc Nguyen, 408-630-2632




Notice to Public:

The Santa Clara Valley Water District publishes meeting agendas two Fridays prior to regular meetings, and publishes amended and special meeting agendas one Friday prior. During the process of amending an agenda, individual links to Board Agenda Reports may not be available. In these cases, please reference the “Full Agenda Package” instead.