Skip to main content
File #: 23-1132    Version: 2 Name:
Type: Time Certain Item Status: Agenda Ready
File created: 10/17/2023 In control: Board of Directors
On agenda: 11/17/2023 Final action:
Title: Update on South San Francisco Bay Shoreline Phase I Project.
Attachments: 1. Attachment 1: PowerPoint

BOARD AGENDA MEMORANDUM

 

Government Code § 84308 Applies:  Yes    No 
(If “YES” Complete Attachment A - Gov. Code § 84308)

 

SUBJECT:

Title

Update on South San Francisco Bay Shoreline Phase I Project.

 

 

End

RECOMMENDATION:

Recommendation

That the Santa Clara Valley Water District (Valley Water) Board and the City of San José (City) Mayor and City Council receive an update on the South San Francisco Bay Shoreline Phase I Project and Pond A18.

 

 

Body

SUMMARY:

The South San Francisco Bay Shoreline Phase I Project (Project) is a multi-benefit flood risk reduction and shoreline restoration project managed by the United States Army Corps of Engineers (USACE) in partnership with Valley Water and the California State Coastal Conservancy (Conservancy). The Project will provide 100-year coastal flood risk management, including consideration for future sea level rise, for the community of Alviso and parts of North San Jose and for critical infrastructure such as the San José-Santa Clara Regional Wastewater Facility (RWF). The Project will also restore roughly 2,900 acres of former salt ponds into tidal marsh and improve public access along the shoreline.

 

The Project consists of five reaches: Reaches 1-3, located between the Alviso Slough and Artesian Slough; and Reaches 4-5, located between Artesian Slough and Coyote Creek. The Project received congressional authorization for design and construction in December 2015 at a cost of $194 million. The Project has since realized significant cost increases, mainly due to significant cost growth of the levee fill material over the years. In February 2021, USACE updated the Project costs to $545 million, nearly tripling the 2015 authorized design and construction cost.

 

The construction contract for Reaches 1-3 was advertised and construction began in December 2021. The construction of Reaches 1-3 is anticipated to be complete in summer 2025. 

 

With the Project cost increase, the Project partners are now exploring ways to lower the remaining cost of the construction of Reaches 4-5 while still meeting the Project objectives.

 

Valley Water and City staff are focused on reducing the cost of the Project and have identified a potential path forward to successfully complete the Project. The City has prepared a draft Letter of Intent describing its proposal to implement that approach and Valley Water staff are currently reviewing the Letter of Intent.

 

Discussion

 

Valley Water and City staff have identified several ways to reduce costs for the Project. A value engineering exercise is underway to determine the most cost-effective route for the remaining levee reaches.

 

To complete Reaches 4-5 and implement the restoration elements, the Project needs approximately 895 acres of land owned by the RWF. The City is the administering agency for RWF and co-owns the RWF with the City of Santa Clara. Valley Water and the City are partnering to develop an approach that would allow the City’s transfer of these lands in a manner that fulfills the City’s fiduciary obligation to the ratepayers of the RWF while reducing the cost of the Project.

 

On August 28, 2019, the San Francisco Bay Regional Water Quality Control Board (Regional Water Board) issued Order No. R2-2019-0026 to the City, requiring the cleanup of 25 legacy biosolids ponds at the RWF known as the Legacy Lagoons. This order requires roughly 60 acres of impacts to wetlands that must be mitigated and provided an opportunity to reduce the burden of those mitigation requirements by working collaboratively on the Project.

 

Other Project needs from the City /RWF include areas for staging, access easements for construction, a right-of-entry agreement for areas needed to stockpile construction materials, and the transfer of Legacy Lagoons L16-L19 and Pond A18 to allow for ecosystem restoration and increased habitat.

 

Opportunities for Partnership

 

Valley Water worked in lock step with the City, the Conservancy, and other stakeholders in 2021 and 2022 to advocate with USACE and Congress for additional federal funding. Thanks to this strong advocacy effort, in February 2023, USACE was awarded an additional $91.12 million under the FY23 Disaster Supplemental Appropriations Bill for the Project.

 

To lower the cost of remaining Project elements, the USACE agreed to a request to conduct a Value Engineering Study (VE). Staff are in the process of gathering information and putting together concepts for the VE analysis. City and Valley Water staff, along with the Project partners, have been meeting monthly and working collaboratively to help progress the Project, provide information towards the VE study, and find ways to lower the Project cost.

 

Valley Water and the City intend to collaborate to secure mitigation credits from the Project’s restoration efforts in Pond A18 with the support of other Project partners: the USACE and the California State Coastal Conservancy. Our partnership when engaging the Regional Water Board is critical to securing these credits, which have the potential to financially benefit both the RWF and the Project. 

 

The City, Valley Water, and Project partners will continue to search for, and discuss, funding opportunities.

 

 

ENVIRONMENTAL JUSTICE IMPACT:

There is no Environmental Justice impact associated with this item.

 

 

FINANCIAL IMPACT:

There is no financial impact associated with this item.

 

 

CEQA:

The recommended action does not constitute a project under CEQA because it does not have a potential for resulting in direct or reasonably foreseeable indirect physical change in the environment.

 

 

ATTACHMENTS:

Attachment 1: PowerPoint

 

 

UNCLASSIFIED MANAGER:

Manager

Bhavani Yerrapotu, Valley Water, (408) 630-2735

Kevin Ice, City of San José, (408) 535-8197

 




Notice to Public:

The Santa Clara Valley Water District publishes meeting agendas two Fridays prior to regular meetings, and publishes amended and special meeting agendas one Friday prior. During the process of amending an agenda, individual links to Board Agenda Reports may not be available. In these cases, please reference the “Full Agenda Package” instead.