File #: 24-1012    Version: 1 Name:
Type: Board of Directors Item Status: Agenda Ready
File created: 11/4/2024 In control: Board of Directors
On agenda: 1/28/2025 Final action:
Title: Consider the January 15th, 2025, Board Audit Committee Recommendation to Approve Performance Audit Assignments for the 2025 Annual Audit Plan, Which Includes Selecting One of Two Options for the Capital Project Delivery Audit, and Provide Further Guidance as Needed.
Attachments: 1. Attachment 1: Audit Scope, Capital Project Delivery, 2. Attachment 2: Audit Scope, Contracting Processes, 3. Attachment 3: Audit Scope, Conservation Strategies, 4. Attachment 4: Audit Scope, Forecasting

BOARD AGENDA MEMORANDUM

 

Government Code § 84308 Applies:  Yes    No 
(If “YES” Complete Attachment A - Gov. Code § 84308)

 

SUBJECT:

Title

Consider the January 15th, 2025, Board Audit Committee Recommendation to Approve Performance Audit Assignments for the 2025 Annual Audit Plan, Which Includes Selecting One of Two Options for the Capital Project Delivery Audit, and Provide Further Guidance as Needed.

 

 

End

RECOMMENDATION:

Recommendation

Consider recommendations resulting from the January 15, 2025, Board Audit Committee meeting to:

A.                     Approve firms to conduct the 2025 Annual Audit Plan including selecting one of two options for the Capital Project Delivery Audit; and

B.                     Provide further guidance as needed.

 

 

Body

SUMMARY:

According to the Board Audit Committee (BAC) Charter, Article I, Paragraph 4 which states “The Committee shall assist the Board, consistent with direction from the full Board, by identifying potential areas for audit and audit priorities, and to review, update, plan and coordinate execution of Board audits.”

Additionally, Article VI, Paragraph 1 states “The Committee shall make recommendations to the full Board for the selection of all Auditors to perform audits in the approved Annual Audit Plan. . ”

At the August 21, 2024, BAC meeting, the Chief Audit Executive (CAE) began discussion of potential audit topics and the process and schedule for completing the proposed Annual Audit Plan for the full Board’s consideration. At the November 20, 2024, BAC meeting, the Committee approved the following four audit topics to be included in the Proposed 2025 Annual Audit Plan:

                     Capital Project Delivery

                     Centralized and Decentralized Contracting Practices

                     Water Conservation Strategies

                     Water Usage and Demand Forecasting

On January 14th, 2025, the Board of Directors (the Board) approved the BAC recommendation of audit topics for the 2025 Annual Audit Plan.  On January 15th, 2025, the BAC members discussed the CAE’s assignment proposal and when audits could reasonably be expected to begin.  The BAC recommends the assignments below including two possible options for the full Board to consider as it relates to the Capital Project Delivery Audit.

1.                     Capital Project Delivery

                     Option 1: assign to Plante Moran with possible start in late Q1 2025 and conclude in Q4 of 2025

                     Option 2: assign to Sjoberg Evashenk with possible start in late Q2 2025 and conclude in Q1 of 2026

 

2.                     Centralized and Decentralized Contracting Practices

                     assign to Sjoberg Evashenk with possible start in Q2 2025 and conclude in Q4 of 2025

 

3.                     Water Conservation Strategies

                     assign to Moss Adams with possible start in Q1 2025 and conclude in Q3 of 2025

 

4.                     Water Usage and Demand Forecasting

                     assign to Moss Adams with possible start in Q3 2025 and conclude in Q1 of 2026

 

The purpose of this item is to obtain the Boards approval of the proposed audit firm assignments to conduct the audits in the approved 2025 Annual Audit Plan.

 

 

ENVIRONMENTAL JUSTICE AND EQUITY IMPACT:

The Annual Audit Plan is not subject to environmental justice analysis. The Annual Audit Plan serves as a tool for communicating audit priorities as determined by the BAC and the Board of Directors.

 

 

FINANCIAL IMPACT:

There is no financial impact associated with this item.

 

 

CEQA:

The recommended action does not constitute a project under CEQA because it does not have a potential for resulting in direct or reasonably foreseeable indirect physical change in the environment.

 

 

ATTACHMENTS:

Attachment 1: Audit Scope, Capital Project Delivery

Attachment 2: Audit Scope, Contracting Processes

Attachment 3: Audit Scope, Conservation Strategies

Attachment 4: Audit Scope, Forecasting

 

 

UNCLASSIFIED MANAGER:

Manager

Darin Taylor, 408-630-3068




Notice to Public:

The Santa Clara Valley Water District publishes meeting agendas two Fridays prior to regular meetings, and publishes amended and special meeting agendas one Friday prior. During the process of amending an agenda, individual links to Board Agenda Reports may not be available. In these cases, please reference the “Full Agenda Package” instead.