BOARD AGENDA MEMORANDUM
Government Code ? 84308 Applies: Yes ? No ?
(If "YES" Complete Attachment A - Gov. Code ? 84308)
SUBJECT: Title
Accept the Work as Complete and Direct the Clerk to File the Notice of Completion of Contract and Acceptance of Work for the Upper Llagas Creek Flood Protection Project, Phase 1 Completion of Milestone 3, Three-Year Mitigation Planting Establishment and Maintenance, Graniterock Company, Contractor, Project No. 26174052, Contract No. C0645 (Morgan Hill, Gilroy, Santa Clara County Unincorporated Area, Including San Martin, District 1).
End
RECOMMENDATION: Recommendation
A. Accept the work on the Upper Llagas Creek Flood Protection Project Phase 1 completion of Milestone 3, Three-Year Mitigation Planting Establishment and Maintenance, Project No. 26174052, Contract No. C0645 as complete; and
B. Direct the Clerk of the Board to sign the Notice of Completion of Contract and Acceptance of Work and submit for recording to the Santa Clara County Clerk-Recorder.
Body
SUMMARY:
The construction contractor, Graniterock Company, has completed Milestone 3 of the Upper Llagas Creek Flood Protection Project Phase 1 (Phase 1 Project), Three-Year Mitigation Planting Establishment Maintenance Period.
Project Background
Santa Clara Valley Water District (Valley Water) is undertaking the Upper Llagas Creek Flood Protection Project (Project) in partnership with the U.S. Army Corps of Engineers (USACE) and the City of Morgan Hill (City) to provide 1% flood protection to approximately 1,100 homes and 500 businesses along West Little Llagas Creek, East Little Llagas Creek, and Llagas Creek. The Project is approximately 13.9 miles long and encompasses the City of Morgan Hill, City of Gilroy, and various unincorporated areas of Santa Clara County, including San Martin. The Project is being constructed in three phases (Phase 1, 2A, and 2B), and flood protection will only be realized after construction of all three phases is completed.
...
Click here for full text