File #: 23-0508    Version: 2 Name:
Type: Watersheds Item Status: Agenda Ready
File created: 4/19/2023 In control: Board of Directors
On agenda: 8/8/2023 Final action:
Title: Approve the Agreement No. A4862S, for Construction and Maintenance, and Agreement No. A4832X, for Operations and Maintenance, with Google LLC. for the Moffett Park Green Link Bordeaux-Borregas Bridge Project for a Portion of Santa Clara Valley Water District's Sunnyvale East and West Channels Flood Protection, Project No. 26074002 (Sunnyvale, District 3).
Attachments: 1. Attachment A: Gov. Code §84308, 2. Attachment 1: Location Map, 3. Attachment 2: Agreement, Cost Share, 4. Attachment 3: Agreement, O&M, 5. Attachment 4: CEQA, Addendum No. 2
BOARD AGENDA MEMORANDUM

Government Code ? 84308 Applies: Yes ? No ?
(If "YES" Complete Attachment A - Gov. Code ? 84308)

SUBJECT:
Title
Approve the Agreement No. A4862S, for Construction and Maintenance, and Agreement No. A4832X, for Operations and Maintenance, with Google LLC. for the Moffett Park Green Link Bordeaux-Borregas Bridge Project for a Portion of Santa Clara Valley Water District's Sunnyvale East and West Channels Flood Protection, Project No. 26074002 (Sunnyvale, District 3).


End
RECOMMENDATION:
Recommendation
A. Consider the environmental effects of modifications to the Sunnyvale East and West Channels Flood Protection Project, as discussed in the second Addendum to the Final Environmental Impact Report;
B. Find that it would be competitively unavailing to advertise and bid the construction of the East Bank and West Bank Floodwalls located near 1212 Bordeaux Drive, Sunnyvale, California (Google Project Reach) using Santa Clara Valley Water District's standard bidding process because competitive bidding would not yield a lower price for constructing these floodwalls than the price negotiated between Google and Santa Clara Valley Water District;
C. Approve the Agreement for the Construction and Maintenance of the Moffett Park Green Link Bordeaux-Borregas Bridge Project with Google, LLC (Google) in the amount of $1,590,608; and
D. Approve the Moffett Park Green Link Bordeaux-Borregas Bridge Project: Operation and Maintenance Agreement.


Body
SUMMARY:
The Sunnyvale East and West Channels Flood Protection Project (Flood Protection Project, Attachment 1) was included in the voter-approved 2012 Safe, Clean Water and Natural Flood Protection Program (Safe, Clean Water Program) and again in 2020 in the voter approved renewed Safe, Clean Water Program as Project E2 under the flood protection priority. The Sunnyvale Flood Protection Project was approved by the Board of Directors in 2014 and will improve conveyance capacity of two existing storm d...

Click here for full text



Notice to Public:

The Santa Clara Valley Water District publishes meeting agendas two Fridays prior to regular meetings, and publishes amended and special meeting agendas one Friday prior. During the process of amending an agenda, individual links to Board Agenda Reports may not be available. In these cases, please reference the “Full Agenda Package” instead.