BOARD AGENDA MEMORANDUM
Government Code ? 84308 Applies: Yes ? No ?
(If "YES" Complete Attachment A - Gov. Code ? 84308)
SUBJECT:
Title
Receive an Overview of the Initially Validated and Currently Unfunded Capital Projects, and the Capital Improvement Program Fiscal Years 2025-29 Five-Year Plan Capital Projects by Fund and Funding Categories.
End
RECOMMENDATION:
Recommendation
A. Review list of Initially Validated and Currently Unfunded Capital Projects;
B. Review the Capital Improvement Program Fiscal Years 2025-29 Five-Year Plan capital projects by Fund and Funding Categories; and
D. Provide feedback as necessary.
Body
SUMMARY:
The annual update of the Capital Improvement Program (CIP) Five-Year Plan includes project plan updates for all existing capital projects and a Validation Process to review and evaluate potential new capital projects for inclusion in the CIP, along with review points for the CIP Committee and decision points for the Board. A presentation that provides an overview of the initially validated and currently unfunded capital projects, along with an overview of the CIP Fiscal Years (FY) 2025-29 Five-Year Plan capital projects by Fund and Funding Categories, is included in the PowerPoint Presentation (Attachment 1).
CIP Development Process Overview
Each year, Santa Clara Valley Water District (Valley Water) staff can submit new projects to be considered for inclusion in Valley Water's CIP. For each potential new project, staff develops a business case to compare capital, non-capital, and non-asset alternative solutions; evaluates the lifecycle costs of these solutions; and identifies a recommended solution that minimizes lifecycle cost while balancing service levels and risk.
From May through September, staff submits the business case for review by their respective Deputy Operating Officer (DOO) or Deputy Administrative Officer (DAO). If staff's respective DOO/DAO approves the project, it is submitted to the CIP coordinator...