BOARD AGENDA MEMORANDUM
Government Code ? 84308 Applies: Yes ? No ?
(If "YES" Complete Attachment A - Gov. Code ? 84308)
SUBJECT: Title
Receive Report of Bids, Ratify Addenda, Approve the Contingency Fund, and Award the Construction Contract to Con-Quest Contractors Inc. for the Penitencia Delivery and Force Main Inspection and Rehabilitation Project, Project No.95084005, Contract No. C0727 in the Sum of $6,591,000 (San Jose, District 3).
End
RECOMMENDATION: Recommendation
A. Ratify Addenda No(s). 1 and 2 to the Contract Documents for Penitencia Delivery and Force Main Inspection and Rehabilitation Project;
B. Award the Construction Contract to Con-Quest Contractors Inc, located in Burlingame, CA, in the sum of $6,591,000; and
C. Approve a contingency sum of $988,650 and authorize the Chief Executive Officer or designee to approve individual change orders up to the designated amount.
Body
SUMMARY:
The objective of the Penitencia Delivery and Force Main Inspection and Rehabilitation Project (Project) is to increase the reliability and useful life of the pipelines.
The Project scope includes completely draining and removing all water from the Penitencia Delivery Main and Penitencia Force Main, performing repairs on pipeline appurtenances, replacing line valves, providing support for an internal pipeline inspection, updating electrical and controls systems, and performing internal pipeline repair work as identified during the inspections.
Project Background
The Penitencia Delivery and Force Main Inspection and Rehabilitation Project is included in the Santa Clara Valley Water District's (Valley Water) Pipeline Maintenance Program (PMP) and is identified as a capital effort in the PMP. The PMP defines the activities associated with maintenance and repair of water supply conveyance systems including pipelines, appurtenances, electrical systems, control systems, and structures, throughout Valley Water's jurisdiction.
The Penitencia Delivery and Force ...