Title: Authorize Distribution of Santa Clara Valley Water District's Capital Improvement Program Draft Fiscal Years 2027-31 Five-Year Plan.
Attachments: 1. *Attachment 1: CIP Draft FY 2027-31 Five-Year Plan, 2. Attachment 2: Project Plan Updates, 3. Attachment 3: PowerPoint
BOARD AGENDA MEMORANDUM

Government Code ? 84308 Applies: Yes ? No ?
(If "YES" Complete Attachment A - Gov. Code ? 84308)

SUBJECT: Title
Authorize Distribution of Santa Clara Valley Water District's Capital Improvement Program Draft Fiscal Years 2027-31 Five-Year Plan.


End
RECOMMENDATION: Recommendation
A. Review the Capital Improvement Program Draft Fiscal Years 2027-31 Five-Year Plan; and
B. Authorize release of the document to all cities and land use authorities in Santa Clara County and the County of Santa Clara for review as to its consistency with their General Plans.


Body
SUMMARY:
Each year, Santa Clara Valley Water District's (Valley Water) Capital Improvement Program (CIP) includes a Five-Year Plan for Board consideration and approval. The CIP Five-Year Plan describes Valley Water's capital investment priorities and provides information on the planned capital projects along with Valley Water's intended source(s) of funding. Staff presents the CIP Five-Year Plan to the Board during the Preliminary and Draft stages for the Board to make decisions and provide direction. The final version of the CIP Five-Year Plan is approved with the annual budget, wherein funding is appropriated to the projects for the following fiscal year.
Capital Investments Not Included in the CIP

Valley Water contributions to water infrastructure capital investments led by external agencies are not included in the CIP Draft FY 2027-31 Five-Year Plan. While not included in the CIP, these investments are evaluated in the Water Supply Master Plan (WSMP) 2050 and budgeted and forecasted through operating projects. They are also included and reflected in the financial modeling that is analyzed during the development of the CIP Five-Year Plan.
These investments include:
1. Sisk Dam Raise Project
2. Delta Conveyance Project
3. Sites Reservoir Project

Additionally, to ensure consistency with Valley Water's various planning efforts, CIP staff continues coordinating with wate...

Click here for full text



Notice to Public:

The Santa Clara Valley Water District publishes meeting agendas two Fridays prior to regular meetings, and publishes amended and special meeting agendas one Friday prior. During the process of amending an agenda, individual links to Board Agenda Reports may not be available. In these cases, please reference the “Full Agenda Package” instead.