Skip to main content
File #: 25-0659    Version: 1 Name:
Type: Assistant CEO Item Status: Agenda Ready
File created: 7/22/2025 In control: Board of Directors
On agenda: 8/26/2025 Final action:
Title: Receive an Update on the Pacheco Reservoir Expansion Project, Project No. 91954002 (Santa Clara County, District 1; Merced County).
Attachments: 1. Attachment 1: May 5, 2025 WSDM Committee Agenda Memo, 2. Attachment 2: PowerPoint
BOARD AGENDA MEMORANDUM

Government Code ? 84308 Applies: Yes ? No ?
(If "YES" Complete Attachment A - Gov. Code ? 84308)

SUBJECT: Title
Receive an Update on the Pacheco Reservoir Expansion Project, Project No. 91954002 (Santa Clara County, District 1; Merced County).


End
RECOMMENDATION: Recommendation
A. Receive an update on the Pacheco Reservoir Expansion Project, and
B. Provide direction to staff and authorize the Interim Chief Executive Officer to take all actions necessary to implement the Board's direction.


Body
SUMMARY:
The purpose of this memorandum is to provide the Board an update on progress made in the planning, permitting, and design efforts of the proposed Pacheco Reservoir Expansion Project ("PREP" or "Pacheco Project") and other issues that may impact the PREP. This memorandum is organized in sections to also address the following concerns raised by the California Water Commission (the "Commission") during its May 21, 2025 meeting:
I. The Commission commented that Valley Water's environmental review and decision-making timeline for the Pacheco Project appears protracted and lengthy.

II. The Commission raised concerns that the likely cost of PREP might be cost-prohibitive for Valley Water.

III. The Commission pointed out that Valley Water has not yet secured the necessary approvals from the Bureau of Reclamation (Bureau) to advance the project.

IV. The Commission observed that PREP does not seem to be a high-priority project for Valley Water compared to other ongoing projects. It also asked when Valley Water's Board would be able to make a decision on the project.

Valley Water continues to make progress in the planning and design phases of the Pacheco Project and has initiated efforts to ensure the timely review and processing of regulatory permits. However, Valley Water continues to face significant challenges with PREP, particularly concerning an anticipated increase in PREP's estimated costs and Valley Water's ability to s...

Click here for full text



Notice to Public:

The Santa Clara Valley Water District publishes meeting agendas two Fridays prior to regular meetings, and publishes amended and special meeting agendas one Friday prior. During the process of amending an agenda, individual links to Board Agenda Reports may not be available. In these cases, please reference the “Full Agenda Package” instead.