File #: 17-0069    Version: 1 Name:
Type: Time Certain Item Status: Agenda Ready
File created: 1/25/2017 In control: Board of Directors
On agenda: 1/31/2017 Final action:
Title: Resolution Calling for a Water Use Reduction Target Equal to 20 Percent of 2013 Water Use.
Attachments: 1. Attachment 1: SCVWD Resolution 16-55, 2. Attachment 2: Proposed Resolution, with Redlines, 3. Attachment 3: Resolution, 4. Handouts 2.3-A
BOARD AGENDA MEMORANDUM


SUBJECT:
Title
Resolution Calling for a Water Use Reduction Target Equal to 20 Percent of 2013 Water Use.


End
RECOMMENDATION:
Recommendation
Adopt the Resolution CALLING FOR A 20 PERCENT WATER USE REDUCTION TARGET AND A RESTRICTION ON OUTDOOR WATERING OF ORNAMENTAL LANDSCAPES OR LAWNS WITH POTABLE WATER TO A MAXIMUM OF THREE DAYS A WEEK; FURTHER, SUPPORTING LOCAL ENFORCEMENT OF THE WATER WASTE PROHIBITIONS CURRENTLY IN EFFECT BY THE STATE WATER RESOURCES CONTROL BOARD, OR AS MAY BE AMENDED.


Body
SUMMARY:
As a result of ongoing drought conditions, the Board of Directors (Board) approved a resolution (Attachment 1) to call for short term water use reductions of 20 percent on June 14, 2016, which is in effect through January 31, 2017. Staff provided the Board an update on 2016 water supply conditions and 2017 outlook scenarios on January 24, 2017. The Board directed staff to return on January 31, 2017 with a resolution that includes a call for a 20 percent reduction in water use (compared to 2013), a three day per week watering restriction, and that supports local enforcement of the water waste prohibitions that are in effect by the State Water Resources Control Board. Accordingly, a proposed resolution is provided in Attachment 2 (redline/strikeout version) and Attachment 3 (identical but without redline/strikeout).



FINANCIAL IMPACT:
There is no impact to any of the fund reserves. For the Board's information, since February 2014, the drought emergency has incurred costs totaling approximately $46 million detailed in the table that follows:

District Labor
$ 6.1 million
District Services and Supplies
$12.6 million
*?Includes percolation pond clean-up and mercury removal
Board and CEO approval budget adjustments
$27.3 million, the breakdown is as follows:
*?Conservation - $16.4 million (which includes the $4.0 million funded by anticipated incremental FY 16 Ad Valorem tax revenue and $0.9 million from Water Utility operatio...

Click here for full text



Notice to Public:

The Santa Clara Valley Water District publishes meeting agendas two Fridays prior to regular meetings, and publishes amended and special meeting agendas one Friday prior. During the process of amending an agenda, individual links to Board Agenda Reports may not be available. In these cases, please reference the “Full Agenda Package” instead.