File #: 17-0105    Version: 1 Name:
Type: Water Utility Enterprise Item Status: Agenda Ready
File created: 2/16/2017 In control: Board of Directors
On agenda: 3/14/2017 Final action:
Title: Sites Project Authority's Amended and Restated Phase 1 Reservoir Project Agreement.
Attachments: 1. Attachment 1: Sites Phase 1 Agreement, 2. Attachment 2: Exhibit A1, 3. Attachment 3: Exhibit B, 4. Attachment 4: Exhibit C, 5. Attachment 5: Bylaws of the Sites JPA, 6. Attachment 6: Proposal to Participate, 7. Attachment 7: Estimated Revenue Table, 8. Attachment 8: Revisions to Sites Phase 1 Agreement, 9. Attachment 9: Amended Sites JPA Agreement, 10. Attachment 10: PowerPoint
BOARD AGENDA MEMORANDUM


SUBJECT:
Title
Sites Project Authority's Amended and Restated Phase 1 Reservoir Project Agreement.


End
RECOMMENDATION:
Recommendation
Authorize the CEO to execute the Sites Project Authority's Amended and Restated Phase 1 Reservoir Project Agreement and to pay the Sites Joint Power Authority $913,146 towards the current phase of the Sites Reservoir Project expenditures.


Body
SUMMARY:

At the District's July 26, 2016 Board meeting, the Board approved staff's request to submit a Proposal to participate in the Sites Reservoir Project (Project). Staff submitted a Proposal to the Sites Joint Power Authority (Sites JPA) on July 28, 2016. The Proposal obligated the District to negotiate in good faith towards an Amended and Restated Phase 1 Reservoir Project Agreement (Project Agreement) with the Sites JPA. In accordance with the Project Agreement the District is required to make a specified financial contribution to the current phase (Phase 1) of the Project. Phase 1 consists of preparing the Project Proposition 1 Water System Investment Program (WSIP) application and EIR/EIS development. The Project Agreement and the accompanying financial contribution is the subject of the recommendation for Board approval.

The Project Agreement allows the District to join the Project Agreement Committee and become part of the team implementing the Project. It also commits the District to financial participation in the amount of $913,146 through the Phase 1 of Project development. Should the District desire to participate in further phases of the Project future agreements with the Sites JPA would need to be negotiated and executed.


The Project Agreement: 1) specifies how costs will be allocated and votes weighed during Phase 1, 2) clarifies purpose and responsibilities, and 3) identifies tasks needed to complete studies for submittal of a Proposition 1 WSIP application. At the request of District staff, revisions were made to provide early parti...

Click here for full text



Notice to Public:

The Santa Clara Valley Water District publishes meeting agendas two Fridays prior to regular meetings, and publishes amended and special meeting agendas one Friday prior. During the process of amending an agenda, individual links to Board Agenda Reports may not be available. In these cases, please reference the “Full Agenda Package” instead.