File #: 17-0147    Version: 1 Name:
Type: Board of Directors Item Status: Agenda Ready
File created: 3/2/2017 In control: Board of Directors
On agenda: 3/14/2017 Final action:
Title: Recommendation from the Pacheco Reservoir Exploratory Ad Hoc Committee to Authorize the Interim CEO to execute the Principles of Agreement - Submittal of Proposition 1 Application and Joint Investigation of Pacheco Reservoir Expansion.
Attachments: 1. Attachment 1: Principles of Agreement

BOARD AGENDA MEMORANDUM

 

 

SUBJECT:

Title

Recommendation from the Pacheco Reservoir Exploratory Ad Hoc Committee to Authorize the Interim CEO to execute the Principles of Agreement - Submittal of Proposition 1 Application and Joint Investigation of Pacheco Reservoir Expansion.

 

 

End

RECOMMENDATION:

Recommendation

The Pacheco Reservoir Exploratory Ad Hoc Committee recommends that the Board authorize the Interim CEO to execute the Principles of Agreement - Submittal of Proposition 1 Application and Joint Investigation of Pacheco Reservoir Expansion

 

 

Body

SUMMARY:

On February 23, 2017, the Board’s Pacheco Reservoir Exploratory Ad Hoc Committee (Committee) met with board members of the Pacheco Pass Water District (Pacheco Pass) and San Benito County Water District (San Benito) regarding the potential enlargement of Pacheco Reservoir and application for funding from the State’s Proposition 1 Water Storage Investment Program for the reservoir enlargement project.

 

Further, at its regular meeting on February 28, 2017, the Board authorized the Interim CEO to execute a single source consultant agreement to prepare a Proposition 1 funding application for Pacheco Reservoir expansion.

 

In the February 23 Committee meeting, draft principles of agreement among Pacheco Pass, San Benito, and the District were presented and discussed. The principles provide for commitments among the parties for coordination, communication and support to prepare and submit an application for Proposition 1 funding.  Representatives of Pacheco Pass and San Benito executed this document on February 27, 2017 (Attachment 1).  The Committee recommends that the Board authorize the Interim CEO to execute these principles.

 

 

FINANCIAL IMPACT:

This item includes an anticipated reimbursement by San Benito to the District not to exceed $45,000, or 5% of the cost of the consultant agreement, not to exceed $900,000 in project 60042001 for preparing a Proposition 1 funding application.

 

 

CEQA:

The recommended action does not constitute a project under CEQA because it does not have a potential for resulting in direct or reasonably foreseeable indirect change in the physical environment. 

 

 

ATTACHMENTS:

Attachment 1:  Principles of Agreement

 

 

 

UNCLASSIFIED MANAGER:

Manager

Garth Hall, 408-630-2750




Notice to Public:

The Santa Clara Valley Water District publishes meeting agendas two Fridays prior to regular meetings, and publishes amended and special meeting agendas one Friday prior. During the process of amending an agenda, individual links to Board Agenda Reports may not be available. In these cases, please reference the “Full Agenda Package” instead.