No. |
Key Capital Projects |
Project Milestone(s) |
Status |
1 |
Almaden Lake Improvements |
1. Draft EIR - 5/2018 6/2019 12/2019 2. Final EIR & Board Certification - 8/2018 11/2019 7/2020 3. Submit Permit Applications - 12/2018 12/2019 7/2020 4. Complete 30% Design - 9/2018 12/2019 5. Complete 60% Design - 12/2018 11/2019 6/2020 6. Complete 90% Design - 3/2019 2/2020 9/2020 7. Complete Final Design - 5/2019 4/2020 12/2020 |
1. Completed 2. Adjusted 3. Adjusted 4. Completed 5. Adjusted 6. Adjusted 7. Adjusted |
2 |
Stream Stewardship Feasibility Studies |
1. Stevens Creek Fish Passage Evaluation Report - 12/2019 3/2020 2. Metcalf Pond Feasibility Report - 12/2020 3. Ogier Ponds Planning Study Report - 9/2022 6/2021 |
1. Adjusted 2. On Target 3. Adjusted |
3 |
Bolsa Road Fish Passage Improvements |
1. Obtain UPRR encroachment permit application approval on design plans and report - 3/2017 8/2018 1. CEQA initial study - 3/2017 7/2018 2. Obtain regulatory permits - 3/2017 3/2019 3. Begin construction - 6/2017 6/2019 6/2020 |
1. Adjusted 1. Completed 2. Completed 3. Adjusted |
4 |
Mid Coyote Flood Protection Project, Montague Expy. to Tully Rd. |
1. Alternative Analysis - 6/2019 2. Planning Study Report - 1/2020 3/2020 3. USACE Feasibility Study Report - 6/2021 4. Design - 12/2021 5. Begin construction - 1/2022 |
1. Completed 2. Adjusted 3. On Target 4. On Target 5. On Target |
5 |
San Francisquito Creek |
1. Construction for Bay to HWY 101 - 12/2018 2. Final Channel Improvement Design - 6/2017 4/2018 12/2018 6/2020 Middlefield 3. JPA Draft EIR for HWY 101 to Searsville Dam - 6/2017 9/2017 5/2018 3/2019 9/2019 4. USACE Tentatively Selected Plan - 6/2017 9/2017 5/2018 5. USACE Chief’s Report - TBD 4. Submit Permit Application - 4/2020 5. Design of Creek Widening - 11/2020 6. Design of Pope Chaucer Bridge - 11/2020 |
1. Completed 2. Adjusted 3. Completed 4. Completed 5. TBD 4. On Target 5. On Target 6. On Target |
6 |
Permanente Creek |
1. Construction of Permanente Creek Channel Improvements - 12/2018 2. Construction of Rancho San Antonio Detention Basin - 12/2018 12/2019 12/2020 3. Construction of McKelvey Park Detention Basin - 5/2019 12/2019 2/2020 |
1. Completed 2. Adjusted 3. Completed |
7 |
Lower Berryessa Creek, Abel Street to Calaveras Blvd - Phase 2 |
1. In-Channel Construction - 95% Complete12/2019 2. Winterize Channel - Complete12/2019 3. Advertise Berryessa Phase 2B (Lower Calera Creek) - 4/2017 4/2018 6/2019 5/2020 4. Award Berryessa Phase 2B (Lower Calera Creek) - 6/2017 6/2018 8/2019 8/2020 |
1. Completed 2. Completed 3. Adjusted 4. Adjusted |
8 |
Berryessa Creek, Calaveras-I- 680 Milestones |
1. Channel Construction Activities (USACE) - 12/2017 2. Coordinate with County on Replacement of Montague Expressway Bridge - 9/2018 |
1. Complete 2. Complete |
9 |
Guadalupe River-Upper, Southern Pacific Railroad to Blossom Hill Road (R7-12) |
1. Complete Design of Reach 7 (USACE) - 3/2017 12/2017 12/2018 12/2021 Pending federal funding 2. Begin Construction (USACE) - 6/2017 6/2018 6/2019 Pending federal funding 3. Acquire rights-of-way for Reach 7 - 12/2019 12/2021 |
1. Adjusted 2. Adjusted 3. Adjusted |
10 |
Guadalupe River-Tasman Drive to I-880 |
1. Alternative Analysis - 3/2020 2. Planning Study Report - 6/2020 3. Design - 4/2022 4. Begin construction - 7/2022 |
1. On Target 2. On Target 3. On Target 4. On Target |
11 |
Watersheds Asset Rehabilitation Program |
1. Uvas Creek Levee Animal Damage Rehabilitation Project (outboard Levee), Miller to Gilroy Sports Park - 6/2019 2. Uvas Creek Levee Animal Damage Rehabilitation Project (inboard Levee), Miller to Gilroy Sports Park - 12/2019 3. San Tomas Creek (Virginia-Payne) Erosion Repair - 11/2019 4. Barron Creek Erosion Repair - 11/2019 9. Lower Penitencia Creek Erosion Repair - 11/2019 5. Calabazas Creek Rehabilitation - 11/2022 6. Piedmont Creek Erosion Repair - 11/2021 |
1. Completed 2. Completed 3. Completed 4. Completed 5. On Target 6. On Target |
12 |
San Francisco Bay Shoreline EIA 11 & EIAs 1-10 |
1. EIA* 11 Provide Local Cost-Share to USACE - 10/2018 & 4/2019 12/2019 & 4/2020 2. EIA 11 Support Design & Construction Phase Effort - Ongoing 3. EIA 11 Acquire right of ways - 9/2021 4. EIAs 1-10 Provide Local Cost Share to USACE for feasibility - 10/2019 & 1/2020 5. EIA 4 & 5 Provide Local Cost Share to SBSPRP - Ongoing |
1. On Target 2. On Target 3. On Target 4. On Target 5. On Target |
13 |
Llagas Creek-Upper, Buena Vista Ave. to Llagas Rd. |
1. Acquire Resource Agency Permits - 12/2016 2/2017 7/2017 7/2018 3/2019 2. Complete Acquisition of Rights-of-Way Phase 1 (Reach 4, 7A, and Lake Silveira) - 12/2016 6/2017 7/2017 7/2018 3/2019 3. Begin Phase 1 Construction - 6/2017 12/2017 12/2018 6/2019 9/2019 4. Complete Phase 2 Design Documents - 6/2017 12/2017 12/2018 7/2019 6/2020 5. Complete Phase 2B Design Documents - 12/2020 |
1. Completed 2. Completed 3. Completed 4. Adjusted 5. On Target |
14 |
Sunnyvale East and West Channels |
1. Submit Permit Applications - 9/2016 12/2016 2/2017 12/2018 6/2019 6/2017 2. Receive Permits - 4/2017 12/2017 12/2018 12/2019 12/2020 |
1. Completed 2. Adjusted |
15 |
Cunningham Flood Detention Certification |
1. Design & Construction Docs - 3/2018 2. Obtain Regulatory Permits and Advertise for Construction - 4/2018 3. Begin Construction - 6/2018 4. Complete Construction - 12/2019 |
1. Completed 2. Completed 3. Completed 4. Completed |
16 |
Palo Alto Flood Basin Tide Gate Structure Replacement, Lower Peninsula |
1. Draft CEQA MND - 12/2018 12/2019 5/2020 2. 60% Design - 11/2019 10/2020 3. Final Design - 5/2020 2/2021 4. Begin Construction - 9/2020 9/2021 |
1. Adjusted 2. Adjusted 3. Adjusted 4. Adjusted |
17 |
Lower Penitencia Creek Improvements, Berryessa Creek to Coyote Creek |
1. Receive Final Permits - 9/2018 4/2019 3/2020 2. Final Design - 9/2018 4/2019 3/2020 3. Advertise Project for Construction - 10/2018 6/2019 4/2020 |
1. Adjusted 2. Adjusted 3. Adjusted |
18 |
Upper Penitencia Creek, Coyote Creek to Dorel Dr. |
1. Planning Study Report - 6/2019 6/2020 |
1. Adjusted |