File #: 20-1061    Version: 1 Name:
Type: Consent Calendar Item Status: Agenda Ready
File created: 11/4/2020 In control: Board of Directors
On agenda: 1/26/2021 Final action:
Title: Adopt Resolution Setting Time and Date of Public Hearing on the Engineer's Report and CEQA Exemption Determination for the Pacheco Pumping Plant Electrical Current Limiting Fuse & Hydraulic Valve Operation System Upgrades, Small Capital Improvements, San Felipe Reach 1, Project No. 91214010, (Merced County, District 1).
Attachments: 1. Attachment 1: Resolution, 2. Attachment 2: Engineer's Report, 3. Attachment 3: Notice of Public Hearing
BOARD AGENDA MEMORANDUM


SUBJECT:
Title
Adopt Resolution Setting Time and Date of Public Hearing on the Engineer's Report and CEQA Exemption Determination for the Pacheco Pumping Plant Electrical Current Limiting Fuse & Hydraulic Valve Operation System Upgrades, Small Capital Improvements, San Felipe Reach 1, Project No. 91214010, (Merced County, District 1).


End
RECOMMENDATION:
Recommendation
Adopt the Resolution SETTING TIME AND DATE OF PUBLIC HEARING ON THE ENGINEER'S REPORT AND CEQA EXEMPTION DETERMINATION FOR THE PACHECO PUMPING PLANT ELECTRICAL CURRENT LIMITING FUSE & HYDRAULIC VALVE OPERATIONS SYSTEM UPGRADES, to occur on February 09, 2021, at 1:00 PM by teleconference Zoom meeting.


Body
SUMMARY:
The District's 5-Year Capital Improvement Program includes annual funding for small capital improvement projects for raw and treated water transmission and water treatment. Capital investments are designated as "small capital projects" if they cost less than $2.5M, can be completed within two fiscal years, and require no right of way acquisition.

The objective of the Project is to reduce the risk of an unplanned event that could result in an occupational injury (electrical arc flash); asset damage (pump motor failure); or pumping plant shutdown (hydraulic valve operating system (HVOS) controls systems failure).

Attachment 1 contains the resolution to set the time and place for the public hearing.

Engineer's Report and CEQA Exemption Determination

Section 12 of the District Act requires the Board to conduct a public hearing to consider all written and oral objections to the proposed project when: 1) the project is new construction; and 2) the project is funded by a single or joint zone of benefit. As the proposed Project meets both conditions, staff has prepared an Engineer's Report (Attachment 2) for the purpose of public disclosure.

In addition, staff has determined that the proposed Project would be exempt from CEQA review because it qualifi...

Click here for full text



Notice to Public:

The Santa Clara Valley Water District publishes meeting agendas two Fridays prior to regular meetings, and publishes amended and special meeting agendas one Friday prior. During the process of amending an agenda, individual links to Board Agenda Reports may not be available. In these cases, please reference the “Full Agenda Package” instead.