Accept the Work as Complete and Direct the Clerk to File the Notice of Completion of Contract and Acceptance of Work for the Rinconada Water Treatment Plant Interim Site Restoration Project, NTK Construction, Inc., Contractor, Project No. 93294057, Contract No. C0670 (Los Gatos) (District 7).
End
RECOMMENDATION:Recommendation
A. Accept the work on the Rinconada Water Treatment Plant Interim Site Restoration Project, NTK Construction, Inc., Contractor, Project No. 93294057, Contract No. C0670 as complete; and
B. Direct the Clerk of the Board to sign the Notice of Completion of Contract and Acceptance of Work and submit for recording to the County of Santa Clara Clerk-Recorder.
Body
SUMMARY:
The Rinconada Water Treatment Plant (RWTP) Interim Site Restoration Project (Project) was important to daily plant operations and was not part of Santa Clara Valley Water District's (Valley Water) previous RWTP Reliability Improvement Project (Reliability Project). This new Project scope was collaboratively developed by Valley Water staff in the Capital, Maintenance, and Operations Units.
The successful completion of this Project will support both the current and future RWTP phases of work. Major items of work included paving, grading, drainage, and stabilization of disturbed areas to restore road and slope surfaces which will prevent erosion and sediment transport. The work also included installation of drainage infrastructure and removal of temporary sump pumps, and other miscellaneous mechanical work associated with process pumps and piping.
Project Background
The RWTP was completed in 1967 and is Valley Water's second largest plant. RWTP has the capacity to deliver up to 80 million gallons of water each day to retailers who then supply residential and commercial users. The RWTP draws water from the South Bay Aqueduct, the San Luis Reservoir, as well as the Anderson and Calero Reservoirs.